Slideshow Other Albums

001_Digging.jpg
Need steps to get up from the new driveway to the previously unused front door. Tarps down. Starting to dig.

002_Digging.jpg
Have to remove several feet of dirt.

003_Digging.jpg
Still digging...

004_Hauling.jpg
Have dumped lots of crushed stone, and laid one full 9 foot step (6 foot slab and 3 foot slab). Now filling behind for the next step.

005_Dumping.jpg
About 5 wheelbarrows of crushed stone per step. Counting the new gravel driveway, we've spead and packed about 60 tons of stone, so far.

006_Tamping.jpg
Pack it down thoroughly every 2 inches of height, so nothing settles in future years.

007_Leveling.jpg
Get the packed crushed stone exactly level with the previous step since the next step will sit partly on each.

008_OneAndAHalfSteps.jpg
One and a half steps done.

009_TwoSteps.jpg
Two steps done and leveled so the rainwater will drain properly.

010_ThreeSteps.jpg
Three steps done. Looks easy, eh? That's because there's no one to take pictures when we are both struggling with a 720 pound 6 foot slab.

011_FourSteps.jpg
Fourth step done and levelled. You can start to see what it's going to look like.

012_TakeABreak.jpg
Taking a break... With all the digging, backfilling, packing, installing slab, adjusting, removing, adding/removing crushed stone, re-packing, re-installing, etc., we're averaging about 1-2 steps per weekend.

013_SlateLanding.jpg
Slate landing at the top of the first 4 steps. Then we'll turn right and go up 3 more steps.

014_Digging.jpg
Steps covered with tarp, while we start digging out the foundation of the new stone wall.

015_TemporarySlabStorage.jpg
Temporary storage of the remaining slabs against the old brick stoop that will eventually be torn out.

016_Starting1stRowOfRightWall.jpg
Digging the foundation for the wall and placing the first row of stones, which will be entirely buried.

017_Starting2ndRowOfRightWall.jpg
Piecing the wall together like a jigsaw puzzle. However, there is no one right way to do it, so Brita does lots of tinkering until she is satisfied. Notice the funky shaped rock on top. You'll see it in later pictures.

018_2ndRowOfRightWall.jpg
Starting to look a little like a wall now.

019_3rdRowOfRightWall.jpg
Assembling a nice neat wall out of irregular stones is slow going. Trying to get them to go nicely up a flight of steps is much worse. Everything has to be level, and fit neatly into the steps, and be heavy enough to not shift over time, even if an adult walks along the wall. These stones are relatively small -- only 300-400 pounds each.

020_TopOfRightWall.jpg
Now it's taking shape!

021_BigRockLeaning.jpg
We've hand picked some of the largest stones to be capstones, the top row of the wall. The one leaning against the wall weighs about 500-600 pounds. Together we can't lift it up into the air, but we can flop it, lean it, and wrestle it into place.

022_RightWallGrowing.jpg
Now you can see the overall effect of the wall and steps.

023_RightWallCloseup.jpg
A closeup. Hey, if I stop taking pictures, I have to go back to slugging rocks...

024_RightWallLeftHalf.jpg
We're very happy with how level the top came out. Putting the biggest rocks on last means you spend a lot of time putting them on, deciding they're too high or low, taking them off, tearing apart and rebuilding the wall below them, putting them back, etc. It's like putting together a very heavy jigsaw puzzle when there's no guarantee that all the pieces are there. Do you recognize the first oddly shaped puzzle piece near the bottom left/middle, from picture 17?

025_RightWallRightHalf.jpg
Closeup of the right half of this stretch of the wall. Still have a long way to go to the right, and around the corner of the driveway, and do it all again on the other side of the steps, and then finish the remaining 3 steps up to the house, ...

026_TurnTheCorner.jpg
Turn the corner and finish off the end with really big rocks for stability.

027_CornerCloseup.jpg
Interlocking the stones at the corner hides half of each stone, but makes it stronger.

028_10MoreTonsOfWallStone.jpg
10 more tons of wall stone to build the left wall and upper platform.

029_24MoreTonsOfCrushedStone.jpg
24 more tons of crushed stone behind/under the wall stone. But, 5 of that is already moved to the upper platform foundation, so really only 19 more tons to move. Piece of cake!

030_StillSomeRoomToPark.jpg
Parking is getting to be a problem. Especially once we start spreading out the wall stone to be able to pick and choose from lots of pieces. We may still be able to park two cars, but turning around in the driveway may not be possible for a while.

031_DigUpperLandingFoundation.jpg
Dig a foundation to support the upper landing.

032_18InchesDeep.jpg
18 inches deep may be overkill, but we don't want it to settle.

033_FillWithCrushedStone.jpg
5 tons, 3 cubic yards, 30 wheelbarrows, 600 shovels, of crushed stone is a lot to move in one day. Tamped down thoroughly every couple inches.

034_1stRowOfUpperLandingWall.jpg
The double row of stones in the base course must be level, so the wall doesn't lean.

035_1stRowBackCorner.jpg
Solid foundation under the back corner too.

036_2ndRowStarted.jpg
2nd row starting to take shape.

037_WhichRockToChooseNext.jpg
Lots of jigsaw pieces scattered about. Which to choose next?

038_3rdRowStarted.jpg
3rd row halfway done

039_SmallRocks.jpg
While Brita was building the wall, Fred was sorting the pile of stones. These are small stones, probably all under 100 pounds.

040_MediumCapStones.jpg
Some nice flat well-shaped cap stones, mostly under 200 pounds.

041_LargeCapStones.jpg
Larger cap stones, 200-500 pounds.

042_HugeStones.jpg
Hard to tell exactly due to the irregular shape, but the one on the left must be at least 500 to 600 pounds. It's 4 feet long, 18 inches wide (at the medium wide section in the middle), and 9 inches thick, so it could be as much as 720 pounds like the stone steps, but it didn't feel quite that heavy. Even wearing my weight-lifter's belt and using a 6-foot pry bar, I couldn't quite get it on the hand truck by myself. Brita and I had to do this one together.

043_5thRowStarted.jpg
Started the 5th (final) row. Took 3 days to build the 4th row to match the long massive 5th row capstone. Lifted that capstone up and down hundreds of times to get it right. None of these 4th row stones made the final cut.

044_5thRowBackSideNeedsWork.jpg
Have to build the front and back of the wall separately to properly support the massive capstones.

045_BuryElectricalConduit.jpg
Bury PVC pipe to use as electrical conduit. Will slide the wires through them later.

046_ElectricityEverywhere.jpg
Not sure yet where we'll want lights and such, so run the conduit to every possible corner that would otherwise be inaccessible under the tons of stone.

047_CrushedStone3FeetDeep.jpg
Many wheelbarrows later, the crushed stone is now nearly 3 feet deep. The front door is now almost usable.

048_5thRowFinished.jpg
The 5th row across the front is finally finished. One row is entirely underground. The center capstone is 4.5 feet long and weighs about 360 pounds. I'm tired of lifting it.

049_PlatformFrontView.jpg
This angled front view is what you see pulling in the driveway and walking up the first flight of steps. Looks good, but most will eventually be hidden by plants.

050_NoStairsUpPlatformYet.jpg
We've topped up the gravel inside the wall, but not yet built the 2nd flight of steps. A gravel ramp leads to the front door.

051_PlatformRightView.jpg
The right side of the platform will almost never be visible. Most of it buried, and the rest will be hidden by plants, even if you did climb over the lower wall and circle around into this nook.

052_PlatformTopView.jpg
The stones had to fit together well in the top row, not only to hold all the gravel, but also because they will be visible from above even after we put the slate landing on top of the gravel. We wanted as straight an edge as possible along the inside of the stone wall, so it will fit nicely against the slate.

053_LeftWallStarted.jpg
Started building the wall on the left of the staircase to match the one on the right. Can also see the new 5x7 entryway we've recently had built onto the front of the house, and the new roof with one-foot overhangs. Compare with picture 1.

054_LeftWallStartedCloseup.jpg
We hand-picked some big curved stones at the quarry to make this curved wall.

055_3FootSlabOnRollers.jpg
Roll a slab into place on rollers of PVC pipe.

056_3FootSlabOnLongRollers.jpg
These thin rollers must be extra long so we can slide the slab along them off of the underlying slab onto the gravel bed.

057_Level3And6FootSlabs.jpg
Level the 3 foot and 6 foot slabs precisely, and frame out the rest of the platform with small (120 pound) pieces.

058_SixSteps.jpg
Six steps now done. Can you tell that the entire 5th and 6th steps are moved two inches to the left? Look at the 6-inch gap between the right side of the 5th step and the top of the lower stone wall that hits the front of the 4th step. In the previous picture it was 4 inches. After positioning the 5th and 6th steps, we found that the 7th step was accidentally cut 2 inches shorter than the rest by the guys at the quarry, and we had to tear out and redo those 2 steps. Not our happiest moment!

059_SixStepsFromAbove.jpg
Lots of tools and other clutter, but it's all coming together. One more step to go. Hopefully no more wrong sizes. Brita had it all planned out to the nearest quarter inch before we had the addition built, and before we even placed the very first stone over two years ago. We'll know soon if we got it right!

060_7thStepOn5thStep.jpg
Dragged the 720-pound 7th step across the yard on rollers made of 2-inch PVC pipe. Then levered it up onto blocks in front of the 5th step. Then, slid it across on 1-inch PVC rollers onto the top of the 5th step. The levered it up onto blocks in front of the 6th step. More work than the first 4 steps where we were bringing the slabs down from above, not up from below, so we didn't have to cross the existing steps.

061_7thStepOn6thStep.jpg
Slid the 7th step across on 1-inch PVC rollers onto the top of the 6th step.

062_BackSideOf7thStep.jpg
Have to fill, level, and smooth the crushed stone base before sliding the 7th step into place.

063_SquareOffTheConcreteFoundation.jpg
Had to chip away 2x6x18 inches of concrete from the foundation of the new addition. The concrete forms had bowed and almost burst when the contractor did a 4-foot deep pour with concrete that was slightly too wet and runny. No problem. Just got a thicker, more solid foundation. 10 inches thick in some places instead of 8. However, some of that bulge got in the way when laying the steps, and had to be chipped away. Tried chisels, pickaxe, etc., and finally got it done with the pointed end of a 6-foot steel "slate bar".

064_7thStepInPlace.jpg
7th step in place. May not get much more done this year. Starting to snow.

065_TightAgainstTheHouse.jpg
Step butted tightly up against the house where we chipped away the concrete.

066_AllSevenSteps.jpg
7 steps, but no slate landings yet. You can see the flow -- up 4 steps and turn right for 3 more steps.

067_SlateLandingInTheSnow.jpg
Quickly threw down a slate landing before the snow started to stick. Next morning that proved worthwhile. No more tracking mud and gravel bits into the house.

068_SlateLandingWithoutSnow.jpg
Even without the cracks filled, the landing shovels off pretty well. Dries quick in the sun too.

069_BothSlateLandings.jpg
Both slate landings now installed, cracks filled, and some plantings done.

070_LeftWallCompleted.jpg
Left wall completed.  Nice S curve.

071_LeftWallFront.jpg
Left wall from the front.  Those stones don't look so big...

072_LeftWallEndWithTools.jpg
End of left wall  Finally used the 600 pound cap stone!  Tools of the trade: 6-foot digging bar for prying; PVC pipe for sliding; hand truck for hauling.

073_LeftWallEndWithFred.jpg
Fred sitting on wall with feet dangling.  Now you can see how big that rock is!

074_ViewUpDrivewayLeftWall.jpg
View of the left wall as you come up the driveway.  Still need some plantings on the left side.

075_ViewUpDrivewayRightWall.jpg
View of the right wall as you come up the driveway.

076_StairsFromDriveway.jpg
Stairs and entryway as you walk from your car.